Arcade Street Bridge

Owner: State of Minnesota

Construction Manager: State of Minnesota,
..............................Dave Reinsch 651-779-5013
Designer: Bridge Division
..................St. Paul - Public Works
Builder:....CS McCrossan, Maple Grove, MN

Est. Cost: $3,100,000

Traffic: Open to Traffic November 7, 2002

The bike trail under the bridge will be detoured around the construction site. The bike trail will , will be opened under the bridge during the fall bike rally weekend.

Construction 8/6/2002

The north and south abutments are complete as well as all the Piers. All of the beams have been set into position. Forming of the deck slab is about one third completed.

Construction 4/26/2002

The piling and footing pads for 3 of the 6 new piers are nearly completed. The three south piers are still in place and can be seen in the background.

Construction 4/26/2002

The north abutment piling is nearly complete. The piling has been cut off to the planned elevation. A concrete footing will be placed over the top of the piling.