Ford Bridge Redecking 2002-2004
**A construction contract has been awarded to Edward Kramer and Sons**
**Construction began July 22, 2002**
The project includes complete replacement of the deck. The arches, main piers and spandrel columns will be repaired.
Construction is expected to begin the summer of 2002 and be completed at the end of 2004, a 3 year project.
The bridge will be open to a lane of traffic in each direction and one sidewalk will remain open. Ramsey County
and Hennepin County are the owners of the bridge.The counties are partnering with MNDOT and the cities of
Minneapolis and Saint Paul to complete the project. The estimated cost of the construction is $17 to 18 million.
Proposed Cross-Section
1996 photo of the Ford Parkway Bridge

1927 photo of the bridge during original construction.
Existing slab and beams removed New beam formed
|
Questions or comments about this web page, please email to:
bridgeweb@ci.stpaul.mn.us
Nov, 2003 |
Division of Bridges
City of Saint Paul, Dept. of Public Works 25 West 4th Street, CHA 1000 Saint Paul, MN 55102 phone 651-266-6180 |